  • Weather permitting, the north half of Parking Lot D (near the Lee Center) at the Des Plaines Campus will be closed from July 17 - 25 for work related to Exterior Lighting Upgrades. The south half of Parking Lot D will re-open to vehicle and pedestrian traffic July 17.
  • The Des Plaines campus Library and Learning Center have moved to their temporary location in the TenHoeve wing (1600 rooms). The TenHoeve Rooms at the Des Plaines campus will be unavailable for events and meetings until Dec. 31, 2025.
  • The Des Plaines Testing Center has moved into its permanent home in Suite 1830 (near the Enrollment Center) and is now open.
  • The Des Plaines Access and Disability Resource Center (ADRC) office has moved to its permanent home in Suite 1820 and is now open.
  • The Division of Student Affairs has temporarily re-located to Room 2817.
An image of the Oakton College Leaf on a grey b

Des Plaines and RHC (Skokie) Campus Exterior Lighting Upgrades

Stakeholder(s):

General campus community

Percent Complete:

 

Project Start:

July 1, 2025

Project Completion:

Summer 2026

Work is expected to begin in early July, resulting in rolling closures of parking lots and walkways, restricting access to vehicle and pedestrian classes for various time durations.

Weather permitting, the north half of Parking Lot D (near the Lee Center) at the Des Plaines Campus will be closed from July 17 - 25. 

Rendering of the new Oakton Library Learning Commons.

Des Plaines Library Learning Commons 

Stakeholder(s):

Library, Learning Center, Center for Teaching Innovation, Math Labs (STEM), TRIO, IT Help Desk

Percent Complete:

 35%

Project Start:

 March 31, 2025

Project Completion:

 Late 2025

The mechanical, electrical and plumbing (MEP) rough-in is ongoing and is expected to continue for several months. Painting of walls is ongoing. The installation of ceilings is ongoing. Tile work for restrooms is completed.
An image of the new door and hardware replacement at Oakton College.

Door and Hardware Replacement

Percent Complete:

10%

Project Start:

TBD

Project Completion:

TBD

The project will be going out for bid in June. Board of Trustees consideration for the bid approval is expected to take place in August.

An image of the Oakton College Leaf on a grey b

Student Affairs, Information Technology and Access and Disability Resource Center (ADRC) Office Renovations (Des Plaines)

Stakeholder(s):

Office of Student Affairs, Oakton IT, ADRC, Testing Center, Workforce Development, Bookstore, Welcome Center

Percent Complete:

 5%

Project Start:

Project Completion:

Phase 1 projects for the IT Hub, Testing Center, and ADRC are nearing completion. 

The Des Plaines Testing Center has moved into its permanent home in Suite 1830 (near the Enrollment Center) and is now open.

The Des Plaines Access and Disability Resource Center (ADRC) office has moved to its permanent home in Suite 1820 and is now open.

Phase 2 projects for the Office of Student Affairs, Workforce Development, Bookstore, and Welcome Center are in design.